不具合の解決

バックグラウンド

If you receive materials that are unacceptable, damaged, over, or short, Procore creates a 'defect' once you finalize the receipt. This allows you to track and resolve the issue directly within the Materials tool.

考慮すべきこと

  • 必要なユーザー権限

  • A defect is generated when you finalize the item's receipt.

  • After you resolve a defect, the 'Quantity Available' for the line item is adjusted in your inventory based on your selection.

前提 条件

ステップス

  1. Navigate to the project's Materials tool.

  2. Click the Defects tab.

  3. Click the defect ticket number.

  4. Click Resolve for the line item.

  5. Select how the resolution impacts inventory.

    • Resolve and add to inventory.

    • Resolve without adding to inventory.

  6. Enter notes about how the issue was resolved.

  7. Click Resolve to finalize.