Add Scheduled Work Entries (iOS)
Objective
To add Scheduled Work entries to the Daily Log using the Procore app on an iOS mobile device.
Things to Consider
- Required User Permissions:
- To create entries:
- 'Standard' or 'Admin' level permissions on the project's Daily Log tool.
- To create pending entries as a collaborator:
- 'Read Only' or 'Standard' permissions to the Daily Log tool with the 'Collaborator Entry Only' granular permission enabled on your permissions template. See Create Daily Log Entries as a Collaborator.
- To create entries:
- Additional Information:
- Information such as the resource and task name can be carried over to the Scheduled Work log from the project's schedule. If you want this information to be populated automatically, ensure the following prerequisites are met:
- A schedule file, such as a Microsoft Project file, must be uploaded to the project's Schedule tool. See Upload a Project Schedule File to Procore's Web Application.
- The schedule file must include resource assignments on the project's tasks. Refer to your schedule program's support resources for specific instruction
- You can configure what items are created with the
- Information such as the resource and task name can be carried over to the Scheduled Work log from the project's schedule. If you want this information to be populated automatically, ensure the following prerequisites are met: