メインコンテンツまでスキップ
Procore

Create a Prime Contract from an Estimate

Objective

To create a prime contract from an estimate in a Procore project.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions to the project's Estimating AND Budget tools.
  • Additional Information:
    • The estimate has to be sent to the budget before you can create a prime contract. 

Steps

  1. Navigate to the project's Estimating tool.
  2. Click the Estimating tab.
  3. Select the estimate.
    estimate-selection-menu.png
  4. Click the Actions menu.
    estimate-actions-menu.png
  5. Select Create Prime Contract.
  6. Choose grouping and accounting options. 
  7. Click Send to Prime Contract.
    send-to-prime-contract.png